Full fibre network deployment

Maltby, Wickersley, Dinnington, Killamarsh and Thunscoe, England

Full fibre network deployment

Trace successfully delivered a large-scale Full Fibre project between February 2022 and June 2024, supporting the expansion of high-speed fibre connectivity across multiple communities.

The project began with TRR (Test, Rod & Rope) activities to prepare and validate existing duct routes ahead of installation works. Trace carried out small civils works including trenching, duct installation, and reinstatement to enable efficient network deployment across the region.

Cable pulling was completed across both spine and distribution routes, alongside the installation of a 288f spine backbone connecting key network cabinets to provide high-capacity connectivity. Extensive fibre splicing works were undertaken throughout the network, followed by full commissioning and testing to ensure optimal performance and service readiness.

The rollout was successfully delivered end-to-end across Maltby, Wickersley, Dinnington, Killamarsh, and Thurnscoe, contributing to approximately 11,388 homes passed and supporting the availability of full fibre broadband services across the area.

The project was completed to a high standard, resulting in a fully operational, tested, and service-ready network.

Key services delivered:

  • TRR (Test, Rod & Rope) duct validation
  • Small civils works, trenching, and reinstatement
  • Cable pulling across spine and distribution routes
  • Installation of 288f spine backbone infrastructure
  • Fibre splicing across network routes
  • Network commissioning and performance testing
  • End-to-end full fibre deployment

Ready to start your project?

Contact our team today to get started on your next connectivity and cabling project.



    Explore our other projects

    CCTV installation – high-definition security deployment

    3 mins

    In January 2026, Trace successfully completed a CCTV installation project, delivering a fully integrated, end-to-end security solution for the client.
    Find out more

    Primark – Body worn camera rollout

    3 mins

    Trace successfully completed a 12-week Body Worn Camera rollout across over 190 Primark stores throughout the UK and Northern Ireland, enhancing store security and operational monitoring.
    Find out more

    Virgin Media O2 – Worden FTTH network deployment

    3 mins

    Trace successfully delivered the Worden FTTH project for Virgin Media O2 between April 2025 and February 2026, supporting the expansion of ultrafast full fibre connectivity within the region.
    Find out more
    Scroll to Top